{"id":193227,"date":"2026-09-11T12:35:31","date_gmt":"2026-09-11T10:35:31","guid":{"rendered":"https:\/\/newmobility.news\/?p=193227"},"modified":"2026-09-11T11:19:46","modified_gmt":"2026-09-11T09:19:46","slug":"liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement","status":"publish","type":"post","link":"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","title":{"rendered":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement"},"content":{"rendered":"The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is 'only' a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to the initia<div class=\"leaky_paywall_message_wrap\"><div id=\"leaky_paywall_message\"><img data-recalc-dims=\"1\" decoding=\"async\" class=\"nag_logo\" src=\"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2022\/02\/nmn-logo-long-transparent-small-4.png?w=300&#038;ssl=1\"  alt=\"New Mobility News\" \/>\r\n\r\n<h2 class=\"text-center\">\r\n\tRead this article now for free!\r\n<\/h2>\r\nRegister a free account and gain access to this article and get more from New Mobility\r\n\n\t\t<div id=\"leaky-paywall-quick-register\" class=\"inline\">\n\t\t\t<form id=\"leaky-paywall-quick-register-form\" method=\"POST\" action=\"\">\n\n\t\t\t\t\n\t\t\t\t\n\t\t\t\t\n\t\t\t\t<p class=\"form-field email-field\">\n\t\t\t\t\t<label for=\"email\">Email<\/label>\n\t\t\t\t\t<input class=\"email\" type=\"email\" name=\"email\" placeholder=\"Enter your email address\" value=\"\" required>\n\t\t\t\t<\/p>\n\n\t\t\t\t\t\t\t\t\t<p class=\"form-field password-field\">\n\t\t\t\t\t\t<label for=\"password\">Password<\/label>\n\t\t\t\t\t\t<input class=\"password\" type=\"password\" name=\"password\" placeholder=\"Create a password\" value=\"\" required>\n\t\t\t\t\t<\/p>\n\t\t\t\t\n\t\t\t\t\n\t\t\t\t<input name=\"company_url\" type=\"text\" value=\"\" autocomplete=\"off\" tabindex=\"-1\" style=\"display:none !important; position:absolute; left:-9999px;\" \/>\n\n\t\t\t\t<input type=\"hidden\" name=\"level_id\" value=\"20\">\n\n\t\t\t\t<input type=\"submit\" value=\"Register for free\">\n\n\t\t\t\t\n\t\t\t<\/form>\n\n\t\t\t<div id=\"leaky-paywall-quick-register-errors\"><\/div>\n\t\t<\/div>\n\n\r\n\r\n<p class=\"text-center\"><strong>\u2014 OR \u2014<\/strong>\r\n\r\n<p class=\"text-center\"><strong>Subscribe now<\/strong> Get unlimited access to the original content of our publishing partners, be alerted on breaking news and get a daily business summary, composed by our specialist journalists, of the top stories about your sector you have to read.<\/p>\r\n\r\n<div class=\"nag_buttons\">\r\n\t<a class=\"button\" href=\"https:\/\/newmobility.news\/subscription\">Subscribe Now<\/a> \r\n\t<span class=\"nag_button_divider\"> or <\/span> \r\n\t<a href=\"https:\/\/newmobility.news\/en\/log-in\/\">SIGN IN<\/a>\r\n<\/div><\/div><\/div>","protected":false},"excerpt":{"rendered":"<p>The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is &#8216;only&#8217; a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to [&hellip;]<\/p>\n","protected":false},"author":164,"featured_media":193261,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_feature_clip_id":0,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"{title}\r\n\r\n{excerpt}\r\n\r\n{url}","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","default_image_id":0,"font":"","enabled":false},"version":2},"_wpas_customize_per_network":false,"jetpack_post_was_ever_published":false},"categories":[77170,7,26,4],"tags":[],"class_list":["post-193227","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-belgium","category-mobility","category-public-transport","category-top-stories-today"],"acf":[],"featured_image_urls_v2":{"full":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1",2440,1512,false],"thumbnail":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=150%2C150&ssl=1",150,150,true],"medium":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=300%2C186&ssl=1",300,186,true],"medium_large":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=640%2C397&ssl=1",640,397,true],"large":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=640%2C397&ssl=1",640,397,true],"1536x1536":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=1536%2C952&ssl=1",1536,952,true],"2048x2048":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2048%2C1269&ssl=1",2048,1269,true],"trp-custom-language-flag":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=18%2C12&ssl=1",18,12,true],"related-thumb":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=640%2C480&ssl=1",640,480,true],"gform-image-choice-sm":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=300%2C300&ssl=1",300,300,true],"gform-image-choice-md":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=400%2C400&ssl=1",400,400,true],"gform-image-choice-lg":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=600%2C600&ssl=1",600,600,true],"mailchimp":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=560%2C347&ssl=1",560,347,true],"unipress-phone":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=640%2C100&ssl=1",640,100,true],"unipress-tablet":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=1536%2C240&ssl=1",1536,240,true],"unipress-tablet-portrait":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=1536%2C180&ssl=1",1536,180,true],"unipress-tablet-landscape":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=2048%2C180&ssl=1",2048,180,true],"unipress-smartphone":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=1080%2C168&ssl=1",1080,168,true],"unipress-wide-screen":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=2440%2C180&ssl=1",2440,180,true]},"post_excerpt_stackable_v2":"<p>The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is &#8216;only&#8217; a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to the initia Read this article now for free! Register a free account and gain access to this article and get more from New Mobility Email Password \u2014 OR \u2014 Subscribe now Get unlimited access to the original content of our publishing partners, be alerted on&hellip;<\/p>\n","category_list_v2":"<a href=\"https:\/\/newmobility.news\/en\/category\/belgium\/\" rel=\"category tag\">Belgium<\/a>, <a href=\"https:\/\/newmobility.news\/en\/category\/mobility\/\" rel=\"category tag\">Mobility<\/a>, <a href=\"https:\/\/newmobility.news\/en\/category\/public-transport\/\" rel=\"category tag\">Public transport<\/a>, <a href=\"https:\/\/newmobility.news\/en\/category\/top-stories-today\/\" rel=\"category tag\">Top Stories Today<\/a>","author_info_v2":{"name":"Luc Joris","url":"https:\/\/newmobility.news\/en\/author\/belga-5\/"},"comments_num_v2":"0 comments","yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.7 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news\" \/>\n<meta property=\"og:description\" content=\"The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is &#039;only&#039; a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to [&hellip;]\" \/>\n<meta property=\"og:url\" content=\"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/\" \/>\n<meta property=\"og:site_name\" content=\"newmobility.news\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/search\/top\/?q=newmobility.news\" \/>\n<meta property=\"article:published_time\" content=\"2026-09-11T10:35:31+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88-1024x635.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1024\" \/>\n\t<meta property=\"og:image:height\" content=\"635\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Luc Joris\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@jorisvry\" \/>\n<meta name=\"twitter:site\" content=\"@jorisvry\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Luc Joris\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\"},\"author\":{\"name\":\"Luc Joris\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/person\\\/9b4a04002179d83e5be74f13c664b722\"},\"headline\":\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement\",\"datePublished\":\"2026-09-11T10:35:31+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\"},\"wordCount\":714,\"publisher\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"articleSection\":[\"Belgium\",\"Mobility\",\"Public transport\",\"Top Stories Today\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\",\"url\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\",\"name\":\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"datePublished\":\"2026-09-11T10:35:31+00:00\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\",\"url\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"contentUrl\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"width\":2440,\"height\":1512,\"caption\":\"The Court of Auditors estimates the cost of the Li\u00e8ge tram at 1.3 billion euros and has made several comments regarding the procedure, including the justification for the project \\\/City of Li\u00e8ge\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/newmobility.news\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#website\",\"url\":\"https:\\\/\\\/newmobility.news\\\/\",\"name\":\"newmobility.news\",\"description\":\"A B2BNews Agency\u00ae news service for mobility business proessional\",\"publisher\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/newmobility.news\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#organization\",\"name\":\"B2BNews Agency\",\"url\":\"https:\\\/\\\/newmobility.news\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2018\\\/01\\\/b2bnews-agency-logo.png\",\"contentUrl\":\"https:\\\/\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2018\\\/01\\\/b2bnews-agency-logo.png\",\"width\":\"581\",\"height\":\"117\",\"caption\":\"B2BNews Agency\"},\"image\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/search\\\/top\\\/?q=newmobility.news\",\"https:\\\/\\\/x.com\\\/jorisvry\",\"https:\\\/\\\/www.linkedin.com\\\/in\\\/jorisvanroy\\\/\",\"https:\\\/\\\/nl.pinterest.com\\\/jorisvanroy\\\/\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/person\\\/9b4a04002179d83e5be74f13c664b722\",\"name\":\"Luc Joris\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g\",\"caption\":\"Luc Joris\"},\"url\":\"https:\\\/\\\/newmobility.news\\\/en\\\/author\\\/belga-5\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","og_locale":"en_US","og_type":"article","og_title":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news","og_description":"The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is 'only' a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to [&hellip;]","og_url":"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","og_site_name":"newmobility.news","article_publisher":"https:\/\/www.facebook.com\/search\/top\/?q=newmobility.news","article_published_time":"2026-09-11T10:35:31+00:00","og_image":[{"width":1024,"height":635,"url":"https:\/\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88-1024x635.png","type":"image\/png"}],"author":"Luc Joris","twitter_card":"summary_large_image","twitter_creator":"@jorisvry","twitter_site":"@jorisvry","twitter_misc":{"Written by":"Luc Joris","Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#article","isPartOf":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/"},"author":{"name":"Luc Joris","@id":"https:\/\/newmobility.news\/#\/schema\/person\/9b4a04002179d83e5be74f13c664b722"},"headline":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement","datePublished":"2026-09-11T10:35:31+00:00","mainEntityOfPage":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/"},"wordCount":714,"publisher":{"@id":"https:\/\/newmobility.news\/#organization"},"image":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","articleSection":["Belgium","Mobility","Public transport","Top Stories Today"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","url":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","name":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news","isPartOf":{"@id":"https:\/\/newmobility.news\/#website"},"primaryImageOfPage":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage"},"image":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","datePublished":"2026-09-11T10:35:31+00:00","breadcrumb":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage","url":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","contentUrl":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","width":2440,"height":1512,"caption":"The Court of Auditors estimates the cost of the Li\u00e8ge tram at 1.3 billion euros and has made several comments regarding the procedure, including the justification for the project \/City of Li\u00e8ge"},{"@type":"BreadcrumbList","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/newmobility.news\/"},{"@type":"ListItem","position":2,"name":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement"}]},{"@type":"WebSite","@id":"https:\/\/newmobility.news\/#website","url":"https:\/\/newmobility.news\/","name":"newmobility.news","description":"A B2BNews Agency\u00ae news service for mobility business proessional","publisher":{"@id":"https:\/\/newmobility.news\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/newmobility.news\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/newmobility.news\/#organization","name":"B2BNews Agency","url":"https:\/\/newmobility.news\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/newmobility.news\/#\/schema\/logo\/image\/","url":"https:\/\/newmobility.news\/wp-content\/uploads\/2018\/01\/b2bnews-agency-logo.png","contentUrl":"https:\/\/newmobility.news\/wp-content\/uploads\/2018\/01\/b2bnews-agency-logo.png","width":"581","height":"117","caption":"B2BNews Agency"},"image":{"@id":"https:\/\/newmobility.news\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/search\/top\/?q=newmobility.news","https:\/\/x.com\/jorisvry","https:\/\/www.linkedin.com\/in\/jorisvanroy\/","https:\/\/nl.pinterest.com\/jorisvanroy\/"]},{"@type":"Person","@id":"https:\/\/newmobility.news\/#\/schema\/person\/9b4a04002179d83e5be74f13c664b722","name":"Luc Joris","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g","caption":"Luc Joris"},"url":"https:\/\/newmobility.news\/en\/author\/belga-5\/"}]}},"jetpack_publicize_connections":[],"jetpack_shortlink":"https:\/\/wp.me\/p9wJdU-Ogz","jetpack_sharing_enabled":true,"jetpack_likes_enabled":true,"jetpack-related-posts":[],"jetpack_featured_media_url":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","_links":{"self":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts\/193227","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/users\/164"}],"replies":[{"embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/comments?post=193227"}],"version-history":[{"count":10,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts\/193227\/revisions"}],"predecessor-version":[{"id":193748,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts\/193227\/revisions\/193748"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/media\/193261"}],"wp:attachment":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/media?parent=193227"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/categories?post=193227"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/tags?post=193227"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}