{"id":193227,"date":"2026-09-11T12:35:31","date_gmt":"2026-09-11T10:35:31","guid":{"rendered":"https:\/\/newmobility.news\/?p=193227"},"modified":"2026-09-11T11:19:46","modified_gmt":"2026-09-11T09:19:46","slug":"liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement","status":"publish","type":"post","link":"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","title":{"rendered":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement"},"content":{"rendered":"<p>The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is 'only' a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to the initial cost estimate for the megaproject.<\/p><p>In the report, the oversight body also cites other points of criticism, such as historical mismanagement at the start of the project, a poorly drafted contract, and inadequate oversight during implementation.<\/p><div class=\"leaky_paywall_message_wrap\"><div id=\"leaky_paywall_message\">This content has been archived. <a href=\"https:\/\/newmobility.news\/en\/subscription\/\">Log in or Subscribe<\/a> to a level that has access to archived content.<\/div><\/div>","protected":false},"excerpt":{"rendered":"<p>The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is &#8216;only&#8217; a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to [&hellip;]<\/p>\n","protected":false},"author":164,"featured_media":193261,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_hide_featured_image":false,"_jetpack_featured_image_duplicate_dismissed":0,"_jetpack_feature_clip_id":0,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"{title}\r\n\r\n{excerpt}\r\n\r\n{url}","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","default_image_id":0,"font":"","enabled":false},"version":2},"_wpas_customize_per_network":false,"jetpack_post_was_ever_published":false},"categories":[77170,7,26,4],"tags":[],"class_list":["post-193227","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-belgium","category-mobility","category-public-transport","category-top-stories-today"],"acf":[],"featured_image_urls_v2":{"full":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1",2440,1512,false],"thumbnail":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=150%2C150&ssl=1",150,150,true],"medium":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=300%2C186&ssl=1",300,186,true],"medium_large":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=640%2C397&ssl=1",640,397,true],"large":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=640%2C397&ssl=1",640,397,true],"1536x1536":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=1536%2C952&ssl=1",1536,952,true],"2048x2048":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2048%2C1269&ssl=1",2048,1269,true],"trp-custom-language-flag":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=18%2C12&ssl=1",18,12,true],"related-thumb":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=640%2C480&ssl=1",640,480,true],"gform-image-choice-sm":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=300%2C300&ssl=1",300,300,true],"gform-image-choice-md":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=400%2C400&ssl=1",400,400,true],"gform-image-choice-lg":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=600%2C600&ssl=1",600,600,true],"mailchimp":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=560%2C347&ssl=1",560,347,true],"unipress-phone":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=640%2C100&ssl=1",640,100,true],"unipress-tablet":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=1536%2C240&ssl=1",1536,240,true],"unipress-tablet-portrait":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=1536%2C180&ssl=1",1536,180,true],"unipress-tablet-landscape":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=2048%2C180&ssl=1",2048,180,true],"unipress-smartphone":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=1080%2C168&ssl=1",1080,168,true],"unipress-wide-screen":["https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?resize=2440%2C180&ssl=1",2440,180,true]},"post_excerpt_stackable_v2":"<p>The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is &#8216;only&#8217; a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to the initial cost estimate for the megaproject.In the report, the oversight body also cites other points of criticism, such as historical mismanagement at the start of the project, a poorly drafted contract, and inadequate oversight during implementation.This content has been archived. Log in or Subscribe&hellip;<\/p>\n","category_list_v2":"<a href=\"https:\/\/newmobility.news\/en\/category\/belgium\/\" rel=\"category tag\">Belgium<\/a>, <a href=\"https:\/\/newmobility.news\/en\/category\/mobility\/\" rel=\"category tag\">Mobility<\/a>, <a href=\"https:\/\/newmobility.news\/en\/category\/public-transport\/\" rel=\"category tag\">Public transport<\/a>, <a href=\"https:\/\/newmobility.news\/en\/category\/top-stories-today\/\" rel=\"category tag\">Top Stories Today<\/a>","author_info_v2":{"name":"Luc Joris","url":"https:\/\/newmobility.news\/en\/author\/belga-5\/"},"comments_num_v2":"0 comments","yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.9 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news\" \/>\n<meta property=\"og:description\" content=\"The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is &#039;only&#039; a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to [&hellip;]\" \/>\n<meta property=\"og:url\" content=\"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/\" \/>\n<meta property=\"og:site_name\" content=\"newmobility.news\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/search\/top\/?q=newmobility.news\" \/>\n<meta property=\"article:published_time\" content=\"2026-09-11T10:35:31+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88-1024x635.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1024\" \/>\n\t<meta property=\"og:image:height\" content=\"635\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Luc Joris\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@jorisvry\" \/>\n<meta name=\"twitter:site\" content=\"@jorisvry\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Luc Joris\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\"},\"author\":{\"name\":\"Luc Joris\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/person\\\/9b4a04002179d83e5be74f13c664b722\"},\"headline\":\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement\",\"datePublished\":\"2026-09-11T10:35:31+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\"},\"wordCount\":714,\"publisher\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"articleSection\":[\"Belgium\",\"Mobility\",\"Public transport\",\"Top Stories Today\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\",\"url\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\",\"name\":\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"datePublished\":\"2026-09-11T10:35:31+00:00\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#primaryimage\",\"url\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"contentUrl\":\"https:\\\/\\\/i0.wp.com\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2026\\\/09\\\/Untitled88.png?fit=2440%2C1512&ssl=1\",\"width\":2440,\"height\":1512,\"caption\":\"The Court of Auditors estimates the cost of the Li\u00e8ge tram at 1.3 billion euros and has made several comments regarding the procedure, including the justification for the project \\\/City of Li\u00e8ge\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/2026\\\/09\\\/11\\\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/newmobility.news\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#website\",\"url\":\"https:\\\/\\\/newmobility.news\\\/\",\"name\":\"newmobility.news\",\"description\":\"A B2BNews Agency\u00ae news service for mobility business proessional\",\"publisher\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/newmobility.news\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#organization\",\"name\":\"B2BNews Agency\",\"url\":\"https:\\\/\\\/newmobility.news\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2018\\\/01\\\/b2bnews-agency-logo.png\",\"contentUrl\":\"https:\\\/\\\/newmobility.news\\\/wp-content\\\/uploads\\\/2018\\\/01\\\/b2bnews-agency-logo.png\",\"width\":\"581\",\"height\":\"117\",\"caption\":\"B2BNews Agency\"},\"image\":{\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/search\\\/top\\\/?q=newmobility.news\",\"https:\\\/\\\/x.com\\\/jorisvry\",\"https:\\\/\\\/www.linkedin.com\\\/in\\\/jorisvanroy\\\/\",\"https:\\\/\\\/nl.pinterest.com\\\/jorisvanroy\\\/\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/newmobility.news\\\/#\\\/schema\\\/person\\\/9b4a04002179d83e5be74f13c664b722\",\"name\":\"Luc Joris\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g\",\"caption\":\"Luc Joris\"},\"url\":\"https:\\\/\\\/newmobility.news\\\/en\\\/author\\\/belga-5\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","og_locale":"en_US","og_type":"article","og_title":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news","og_description":"The total cost of the new tram line in Li\u00e8ge will amount to 1.3 billion euros. That is the conclusion reached by the Court of Auditors in a new report. While this is 'only' a good 139 million euros higher than when the PPP contract was signed in 2019, it represents a doubling compared to [&hellip;]","og_url":"https:\/\/newmobility.news\/en\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","og_site_name":"newmobility.news","article_publisher":"https:\/\/www.facebook.com\/search\/top\/?q=newmobility.news","article_published_time":"2026-09-11T10:35:31+00:00","og_image":[{"width":1024,"height":635,"url":"https:\/\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88-1024x635.png","type":"image\/png"}],"author":"Luc Joris","twitter_card":"summary_large_image","twitter_creator":"@jorisvry","twitter_site":"@jorisvry","twitter_misc":{"Written by":"Luc Joris","Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#article","isPartOf":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/"},"author":{"name":"Luc Joris","@id":"https:\/\/newmobility.news\/#\/schema\/person\/9b4a04002179d83e5be74f13c664b722"},"headline":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement","datePublished":"2026-09-11T10:35:31+00:00","mainEntityOfPage":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/"},"wordCount":714,"publisher":{"@id":"https:\/\/newmobility.news\/#organization"},"image":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","articleSection":["Belgium","Mobility","Public transport","Top Stories Today"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","url":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/","name":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement - newmobility.news","isPartOf":{"@id":"https:\/\/newmobility.news\/#website"},"primaryImageOfPage":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage"},"image":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage"},"thumbnailUrl":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","datePublished":"2026-09-11T10:35:31+00:00","breadcrumb":{"@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#primaryimage","url":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","contentUrl":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","width":2440,"height":1512,"caption":"The Court of Auditors estimates the cost of the Li\u00e8ge tram at 1.3 billion euros and has made several comments regarding the procedure, including the justification for the project \/City of Li\u00e8ge"},{"@type":"BreadcrumbList","@id":"https:\/\/newmobility.news\/2026\/09\/11\/liege-tram-to-cost-e1-3-billion-after-years-of-mismanagement\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/newmobility.news\/"},{"@type":"ListItem","position":2,"name":"Li\u00e8ge tram to cost \u20ac1.3 billion after years of mismanagement"}]},{"@type":"WebSite","@id":"https:\/\/newmobility.news\/#website","url":"https:\/\/newmobility.news\/","name":"newmobility.news","description":"A B2BNews Agency\u00ae news service for mobility business proessional","publisher":{"@id":"https:\/\/newmobility.news\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/newmobility.news\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/newmobility.news\/#organization","name":"B2BNews Agency","url":"https:\/\/newmobility.news\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/newmobility.news\/#\/schema\/logo\/image\/","url":"https:\/\/newmobility.news\/wp-content\/uploads\/2018\/01\/b2bnews-agency-logo.png","contentUrl":"https:\/\/newmobility.news\/wp-content\/uploads\/2018\/01\/b2bnews-agency-logo.png","width":"581","height":"117","caption":"B2BNews Agency"},"image":{"@id":"https:\/\/newmobility.news\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/search\/top\/?q=newmobility.news","https:\/\/x.com\/jorisvry","https:\/\/www.linkedin.com\/in\/jorisvanroy\/","https:\/\/nl.pinterest.com\/jorisvanroy\/"]},{"@type":"Person","@id":"https:\/\/newmobility.news\/#\/schema\/person\/9b4a04002179d83e5be74f13c664b722","name":"Luc Joris","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/9e27cf9984ae903174b14c7dd33d523290f03fd71803b04bc6e486c7259b2920?s=96&d=mm&r=g","caption":"Luc Joris"},"url":"https:\/\/newmobility.news\/en\/author\/belga-5\/"}]}},"jetpack_publicize_connections":[],"jetpack_shortlink":"https:\/\/wp.me\/p9wJdU-Ogz","jetpack_sharing_enabled":true,"jetpack_likes_enabled":true,"jetpack-related-posts":[],"jetpack_featured_media_url":"https:\/\/i0.wp.com\/newmobility.news\/wp-content\/uploads\/2026\/09\/Untitled88.png?fit=2440%2C1512&ssl=1","_links":{"self":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts\/193227","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/users\/164"}],"replies":[{"embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/comments?post=193227"}],"version-history":[{"count":10,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts\/193227\/revisions"}],"predecessor-version":[{"id":193748,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/posts\/193227\/revisions\/193748"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/media\/193261"}],"wp:attachment":[{"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/media?parent=193227"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/categories?post=193227"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/newmobility.news\/en\/wp-json\/wp\/v2\/tags?post=193227"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}