Lantis: ‘New delay for Oosterweel project: completion in 2033’
Completion will be delayed until 2033, but Lantis emphasizes that the Scheldt tunnel connection between the left and right banks and the Oosterweel junction in the north of the city are still on schedule for commissioning in 2030 /Belga
On Wednesday, Lantis reported that the Oosterweel project in Antwerp will not be completed until the end of 2033, three years later than expected. According to the builder, one of the main reasons for the delay is the PFAS pollution. Not only the works in Linkeroever and Zwijndrecht were confronted